EMT Practice Test
1. Question Content...
Question4: Which of the following is true about pure risk?
Question12: The utility of a risk seeker is:
Question13: In your project, if earned value (EV) is larger than planned value (PV)
Question14: For a stakeholder with low interest and high power, the project manager should:
Question17: Drag the interpersonal skill on the left to the correct scenario on the right
Question20: Plan-do-check-act is also known as:
Question25: The end point of a project phase can be referred to as:
Question29: Which of the following factors is lowest at the start of the project?
Question31: A summary WBS is usually developed in the
Question36: 
Based on the project scheduled, how much float is there for activity number 4?
Question44: Which of the following is true regarding product scope descriptions?
Question48: In project management, Work authorization is normally not...
Question53: Which is not an activity included in the Integrated change control process?
Question54: The Plan Stakeholder Management process belongs to which Process Group?
Question66: Participative Management:
Question80: Which statement describes best the purpose of brainstorming sessions?
Question81: Risk mitigation involves______________
Question83: Which of the following is an input to Direct and Manage Project Execution?
Question86: The most common communication problem during negotiations is that
Question87: A lessons learned is BEST completed by:
Question88: A project plan generally includes the following:
Question93: Based on the following table, what is the total float for activity (B)?
Question95: Which of the following is CORRECT about quality improvements?
Question97: An output of scope definition is:
Question98: Which of the following is NOT a valid reason to authorize a project?
Question102: The ISO 9000 standards provide______________
Question105: 80% of the problems are found in 20% of the work is a concept of:
Question109: Drag the interpersonal skill on the left to the correct scenario on the right
Question112: A comprehensive definition of scope management would be:
Question114: Which enterprise environmental factors are considered during cost estimating?
Question115: An input required in Define Scope is an organizational:
Question119: At what stage of a project does the development of a cohesive project team occur?
Question121: There is a project with CPI = 0.81 and TCPI = 1.00001; this project is:
Question122: Analogous Estimate Costs is _________.
Question126: Tools and techniques used in Direct and Manage Project Work include:
Question130: Labor, materials, equipment, and supplies are examples of:
Question131: In Project Cost Management, which input is exclusive to the Determine Budget process?
Question133: Which of the following are valid ways to breakdown the work in a WBS?
Question143: Which type of analysis is used to develop the communications management plan?
Question147: In what knowledge area does Activity Resource Estimating occur?
Question158: Which of the following is an example of the simplest fixed-price contract?
Question161: An example of coercive power would be:
Question165: Management decision-making includes:
Question182: Earned value measurement is an example of:
Question185: Create Procurement document is done in _______.
Question193: Integrated change control includes the following activities EXCEPT:
Question197: Which of the following is not a scope management process?
Question198: The lowest level normally depicted in a work breakdown structure (WBS) is called a/an:
Question199: How is quality control performed?
Question200: Which of the following statement are false?
Question204: An issue log is an input to which Project Human Resource Management process?
Question207: The purpose of a numeric scale in risk management is to______________
Question211: Who is responsible for issuing the project charter?
Question215: A series of consecutive points on the same side of the average is called:
Question216: What is the purpose of the WBS?
Question217: The scope baseline/project charter is prepared by the:
Question225: Which of the following is the BEST candidate for a three-point estimate?
Question227: Which of the following is an input of the Define Activities process?





